We “MACimize” the value of Telecommunications!

[email protected] | 440-735-1932

200 Public Square – Citizens Bank

200 PUBLIC SQUARE CITIZENS BANK
200 Public Square – Citizens Bank
5
Sep

Description of Work

Install a fiber optic extension for service provider.

Our Scope of Work included:

  1. Fiber Optic Cabling
    • Install one (1) – 12 strand single mode fiber optic cable from the mezzanine cross connect room to the customer’s Telecom room to extend LEC services.
    • Provide and install 1 – wall mounted Fiber Optic Housing Unit with 12 strand LC adapter panel, in the Mezzanine cross-connect room.
    • Provide 1 – rack mounted Fiber Optic Housing Unit with 12 strand LC adapter panel at customer Telecom Room.
    • Terminate 12 Fiber Optic Strands to fusion spliced single mode LC connectors on each end (24 connectors).
    • Test and certify fiber optic cable and connectors.
    • Patch into LEC circuit at Mezzanine.
    • Customer to patch in Network Equipment in Telecom Room.
  2. Run cross connects in mezzanine room to extend copper services to the 37th floor riser closet
    • Run Copper cabling from the 37th floor Riser to the Customer’s Telecom Room
    • Terminate to patch panel in customers Telecom Room.
    • Cross connect to LEC services at Mezzanine.
    • Customer to patch into Network Equipment in Telecom Room.
  3. Conduit pathway
    • Furnish and Install (1) 50′ Run Of 2” Conduit.
    • Locate and Identify Twist Lock Circuit, Label and Verify.
    • Furnish and Install (1) 100′ Run Of 1” Conduit Run for Telecommunications Grounding Chase Nipple.
    • Furnish and Install New Telecommunications Grounding Bus Bar.
    • Furnish and Install (1) 6” Recessed Can in The Drop Ceiling Inside Telecommunications Room.
    • Core Drilling (2) 3” & (2) 1.5” Core Drilled Sleeves.
    • Off Normal and Off Work Hours.
  4. Cabinetry work
    • Furnish and Install (1) 50′ Run Of 2” Conduit.
    • Locate and Identify Twist Lock Circuit, Label and Verify.
    • Furnish and Install (1) 100′ Run Of 1” Conduit Run for Telecommunications Grounding Chase Nipple.
    • Furnish and Install New Telecommunications Grounding Bus Bar.
    • Furnish and Install (1) 6” Recessed Can in The Drop Ceiling Inside Telecommunications Room.
    • Core Drilling (2) 3” & (2) 1.5” Core Drilled Sleeves.
    • Off Normal and Off Work Hours.
  5. Provide labor To UPS.
︿
Contact Us

Contact Us

Send us a message and one of our customer service representatives will contact you within 24 hours.

Contact ×
Contact Us
Email Click-to-call 440-735-1932

Contact Us

×
Name(Required)